英国留学生项目管理硕士课程作业范文-Schedule Planning for Tiancheng Synthesis

论文价格: 免费 时间:2013-03-24 21:12:22 来源:www.ukassignment.org 作者:留学作业网

英国留学生项目管理硕士课程作业范文-Schedule Planning for Tiancheng Synthesis Building


目录
0。执行摘要2
第1部分:计划规划和假设3
1。假设宣言“3
1.1项目说明3
1.2进度计划的假设4
2。详细的项目进度计划(见附件)
第2部分:计划管理与控制6
3。进度管理工具概述
3.1工作分解结构(WBS)
3.2甘特图7
3.3计划评审技术(PERT)
4。工作身份的WBS10
4.1分解标准10
4.2工作分解结构建立目标项目11个
5。关键路径时间分析13
6。进度和预算的关系15
6.1预算分析15
6.2之间的交叉分析的时间表和预算18
8。结论和建议20
参考22


调度不是简单的识别事件中存在的项目或让那些系列任务或事件,以符合实际的进展。调度也是一种优化。一些安排是可行的执行,但他们不是最好的。计划的最终目标是发现为了保持最佳的平衡项目的质量,成本的具体计划,项目的时间和其他要求。这一系列的作品不能仅仅通过人们的判断是基于经验和直觉而非科学的推理完成。作为管理科学的一个重要,项目管理已经发展了许多有效的分析工具来解决这些问题。根据这些工具的使用,调度工作的结果可以看作是稳定的和正确的。


Table of Contents
0. Executive Summary 2
Part 1: Schedule Planning & Assumptions 3
1. Assumption Declaration 3
1.1 Project Description 3
1.2 Schedule Planning Assumption 4
2. Detailed Project Schedule Plan (See Appendix) 5
Part 2: Schedule Management & Control 6
3. Overview of Schedule Management Tools 6
3.1 Work Breakdown Structure (WBS) 6
3.2 Gantt Chart 7
3.3 Program Evaluation and Review Technique (PERT) 8
4. Task Identity by WBS 10
4.1 Decomposition Criteria 10
4.2 Work Breakdown Structure Establishment of target project 11
5. Critical Path & Duration Analysis 13
6. Relationship between Schedule and Budget 15
6.1 Budget Analysis 15
6.2 Cross Analysis between Schedule and Budget 18
8. Conclusion & Recommendation 20
Reference 22


0. Executive Summary
Schedule is one of the three main objectives in project management field. A project’s success can be simply defined as to get the job done under the time and cost limitation. Scheduling is the process used to determine the overall project duration and when events and activities are planned to happen (AMP, 2006). Through scheduling, managers can make a clear identification about which tasks or events are the most crucial parts in the whole project. Engineering project progress scheduling and control are very important to the project construction operator (Sears etc., 2008). Organizing the performance progress schedule and timely identifying and adjusting the discrepancy between the practical progress and the scheduled progress are the basic works for the project managers to realize.


However, scheduling is not as simple as to identify which events exist in the project or let those series of tasks or events in order to match the practical progress. Scheduling is also a matter of optimization. Some arrangements which are feasible to executive, but they are not the best. The final target of scheduling is to find out a specific plan in order to keep the best balance of the project quality, cost, time and other requirements of the project. These series of works can not be completed only by people’s judgment which is based on experience or instinct but not scientific ratiocination. As an important of management science, project management has developed a lot of efficient analysis tools to solve those problems stated before. Depending on the usage of these tools, the result of scheduling works can be seen as stable and correct.


This report will mainly focus on the real engineering project practice to show the importance and process of project schedule planning, which is the fundamental of project implementation. The target project is the construction of a Synthesis Building which is consist of a main building and an attached building and located in Jiangsu Province, People’s Republic of China. In order to formulate a proper schedule plan for the target project, a sequence of mature project management tools will be used. First of all, work breakdown structure technique will be used to identify and standardize the events included in the project. And then, network diagram and Gantt chart will be adopted in order to identify the critical path and the mile stone events in the project. Finally, considering keeping the balance of time and cost, a cross-analysis related to those two issues will be used.


Part 1: Schedule Planning & Assumptions
1. Assumption Declaration
1.1 Project Description
Tiancheng Synthesis building is located in a commercial area in Jiangsu Province, People’s Republic of China. The overall construction area is 17205.91m2, including an office building which has 9 floors above the ground (construction area: 9006.00 m2) and a underground parking lot (including the facility floor which is also set underground, construction area: 5336.36 m2) and an attached building which has 2 floors above the ground and used for gym (construction area: 1340 m2) and dining hall (construction area: 1523.55 m2). The plane size of office building is 73 meters long and 17.35 meters wide. The height of first floor of office building is 4.8m and other floors are 3.9m. The plane size of the attached building is 27.9 meters long and 26.7 meters wide, the floor height is as same as the office building. The structure of the synthesis building is cast-in-place reinforced concrete and the foundation form is box foundation in office building part which is supported by the shear walls underground and pile foundation in attached building part. The office building and the attached building are connected by an overline bridge which is assembled in the second floor. Except the influences caused by building size and the foundation form, the other parts of both office building and attached building are the same, including façade decoration (glass curtain wall and stone curtain wall are all used in the two buildings), interior furnishing style, electrical equipment etc.. Besides, this construction project also covers gardening and so on.


1.2 Schedule Planning Assumption
Assumption 1: Time Calculation
1) Gregorian calendar is used when we calculate the time.
2) We assume that the project will be initiated at Nov. 8th, 2011.
3) After the project starts, the project will process continuing without holiday or weekends.
4) All kinds of time-bound are neglected in this part especially the total duration limitation and specific time limitation for individual tasks.
5) All the tasks are set by the Earliest Start Principle which means start as soon as possible.


Assumption 2: Cost Calculation
1) All kinds of costs are exchanged into euro dollars (fixed exchange rate is used depending on the average level in Nov., 2011).
2) Costs are happened at the start of each task.
3) We assumed that taxes, loan interests and price inflation are included in by the cost evaluation.
4) Not to take risk costs into account, for example: extremely weather, nature hazard and engineering claim.


Assumption 3: Project Implementing
1) The field (working face) is large enough so that we do not need take this issue into consideration when making schedule plan.
2) All tasks in the project (both visible and invisible tasks) are clearly and correctly identified without any mistake or neglect.
3) Other resource’ limitations are not considered except cost.


2. Detailed Project Schedule Plan (See Appendix)
Through the detailed project schedule plan, it is easy to figure out that the total duration of the project is 574 days and will be finished at Jan. 17th, 2014. The total cost of this project is €11,095,740.


NOTE: The data used in project scheduling are all authorized by Tiansheng Construction Group which is the general contractor of Tiancheng synthesis building construction project. The relationships between each task and the cost of every task are made based on the historical engineering experience.

此论文免费


如果您有论文代写需求,可以通过下面的方式联系我们
点击联系客服
如果发起不了聊天 请直接添加QQ 923678151
923678151
推荐内容
  • 英国市场营销学essay-T...

    市场营销是英国留学生热门专业之一,而对于市场营销学英文作业的写作让很多学生头疼不已,本文将针对市场包容性问题作出探讨研究。...

  • 指导英国essay-中英教育...

    核心提示:指导英国essay-中英教育制度比较与相关意义 The Comparison and Implication of Education Systems......

  • 指导英国essay论文—同性...

    本文是一篇指导英国essay论文。随着全球化的发展,不同国家和不同人民之间的经济交流和文化交流越来越盛行。在这种情况下,东西方的文化差异正在缩小。然而,东西方之......

  • Essay指导指导范文

    Essay指导范文 Essay指导指导范文 essay格式是什么样的?...

  • 英国文学essay-《傲慢与...

    提供英国文学essay-《傲慢与偏见》的女性叙事视角解析-"Pride and prejudice" female narrative perspective ......

  • 英国essay指导如何识别不...

    英国essay指导如何识别不要被无良商家下套? 找essay指导在国外的高校已经是一条捷径了,越来越透明,所以说也不是一个罕见的现象,一些留学生朋友反馈,通常表......

923678151